If $18$ boys can do a piece of work in $24$ days, then $27$ boys can do the same work in:

Practice this question from Chapter Mock 7: Time and Work, Pipe and Cistern, with options and an explanation.

Question

If $18$ boys can do a piece of work in $24$ days, then $27$ boys can do the same work in:

Option A

12 days

Option B — Correct answer

16 days

Correct choice.

Option C

18 days

Option D

24 days

Explanation

Men and days are inversely proportional for the same work. So required days $=\frac{18\times24}{27}=16$.